Campus · SteamGlobal reference
Columbia University, New York
6,676 kW (≈ 1,900 TR)
Two BROAD steam-driven absorption chillers supply campus cooling. BROAD Group reference project.
Overview
A steam or hot water absorption chiller is an indirect-fired vapour absorption machine (VAM) that uses steam or hot water, instead of electricity or a burner, to drive a lithium bromide-water cooling cycle. BROAD builds it in two forms: single-stage, for low-pressure steam (0.1–1.5 kg/cm²) or 70–95°C hot water at COP 0.7–0.8, and two-stage, for 4.2–10.5 kg/cm² steam or 138–180°C hot water at COP 1.1–1.4.
Most Indian plants that run boilers, turbines, engines or process lines already have steam or hot water to spare. A BROAD steam or hot water absorption chiller uses that heat to make chilled water, so the plant's cooling no longer depends on electric compressors. The only electricity drawn is for the solution and refrigerant pumps and the cooling water system.
The choice between single-stage and two-stage depends on the temperature or pressure of the heat you have. Single-stage machines accept low-grade heat that a two-stage machine cannot use. Two-stage machines need hotter input but give 40–70% more cooling from the same heat.
| Heat source available | BROAD model | COP | Approx. steam use |
|---|---|---|---|
| Low-pressure or waste steam, 0.1–1.5 kg/cm² | Single-stage steam chiller | 0.7–0.8 | ≈ 7.5–8.5 kg/h per TR |
| Hot water, 70–95°C (jacket water, process or solar) | Single-stage hot water chiller | 0.7–0.8 | - |
| Steam, 4.2–10.5 kg/cm² | Two-stage steam chiller (BS) | 1.1–1.4 | ≈ 4.5–5.5 kg/h per TR |
| Hot water, 138–180°C | Two-stage hot water chiller (BH) | 1.1–1.4 | - |
One ton of refrigeration (TR) is 3.517 kW of cooling, so the heat a chiller needs per TR is 3.517 kW divided by its COP. A single-stage machine at COP 0.75 needs about 4.7 kW of heat per TR, roughly 7.5–8.5 kg/h of low-pressure steam. A two-stage machine at COP 1.25 needs about 2.8 kW per TR, roughly 4.5–5.5 kg/h of 8 kg/cm² steam. These are planning estimates; BROAD engineers confirm the figure for your steam conditions during sizing. To turn them into running cost and payback, use the VAM price and payback calculator.
Key specifications
Sizing & price
BROAD supplies the Steam & Hot Water Absorption Chiller from 30–3,300 TR. There is no list price: the cost depends on the capacity you need, the heat source or fuel conditions at your site, the cooling water system and the installation scope. BROAD quotes each project after a sizing study.
For a sizing study, share:
How it works
Steam, hot water, exhaust gas or a gas/oil burner heats the generator. No compressor is needed.
The heat boils water vapour (the refrigerant) out of the lithium bromide solution.
The vapour condenses, then evaporates under deep vacuum, pulling heat out of the chilled-water circuit.
Concentrated lithium bromide re-absorbs the vapour and the solution returns to the generator.
Chilled water leaves for process cooling or air conditioning, with water as a zero-ODP, zero-GWP refrigerant.
Model finder
| Model | Cooling Capacity | Dimensions (L×W×H) | Energy Input |
|---|---|---|---|
| Single-Stage Steam | 100–3,300 TR | Varies by capacity | Steam (0.1–1.5 kg/cm²) |
| Single-Stage Hot Water | 100–3,300 TR | Varies by capacity | Hot Water (70–95°C) |
| BS Model (Two-Stage Steam) | 30–3,300 TR | Varies by capacity | Steam (4.2–10.5 kg/cm²) |
| BH Model (Two-Stage Hot Water) | 30–3,300 TR | Varies by capacity | Hot Water (138–180°C) |
Engineering
Single-stage models use steam from 0.1 kg/cm² and hot water from 70°C, heat that most plants vent or send to cooling towers.
BS and BH two-stage models reach COP 1.1–1.4, giving 40–70% more cooling than single-stage from the same steam.
Control logic protects the lithium bromide solution when steam pressure or hot water temperature fluctuates.
Water is the refrigerant and lithium bromide the absorbent: zero ODP, zero GWP and no refrigerant phase-down risk.
No mechanical compressor in the cooling cycle, so wear and vibration are low and service life runs beyond 25 years.
Business case
At Kejriwal Geotech, Surat, 1,200 TR of steam chillers avoid about 850 kW of electrical load and paid back in roughly 7 months.
Moving cooling off electric compressors cuts the plant's peak electrical demand and frees grid or captive power for production.
Less grid electricity for cooling means lower Scope 2 emissions, with no synthetic refrigerants to report.
Where it’s used
Case studies
Real-world implementations of this technology across industrial facilities.
TextileSurat, Gujarat· 2019–20
1,200 TR · 7-month payback
1,200 TR of process cooling from waste CP steam
Read case study
Campus · SteamGlobal reference
6,676 kW (≈ 1,900 TR)
Two BROAD steam-driven absorption chillers supply campus cooling. BROAD Group reference project.
Steel · Hot waterGlobal reference
8,800 kW (≈ 2,500 TR)
Ten BROAD hot water absorption chillers run on heat recovered from the steel plant. BROAD Group reference project.
Get custom pricing and engineering specifications for the Steam & Hot Water Absorption Chiller.